Work has been progressing well across the Town Homes at Brighton Mills site this summer.

Framing is moving quickly on the Holton Street block. Holton Street framing will be complete by the end of August.

IMG_2876

113-115 and 117-119 Holton Street from park

IMG_2880

121-123 Holton Street

IMG_2869

View of living/dining/kitchen inside 113-115 Holton St

Back on Litchfield Street, the final foundation is being poured this week at 103-105 Litchfield.  Framing and roofing were completed on the 101 and 107 Litchfield buildings.  Mechanical, Electical, and Plumbing (MEP) work is complete at 101 and will finish this week inside 107.  After MEP inspections, insulation work began at 101 and will begin at 107 next week.

IMG_2862

103-105 Litchfield foundation footing walls.

IMG_2865

Ductwork for heating and cooling, ceiling mounted light fixtures, and plumbing for fire sprinklers visible in 107 Litchfield

IMG_2879

Window installation is moving right along behind framing

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s