Town Homes at Brighton Mills Construction Blog

Busy Summer

Leave a comment

The Town Homes at Brighton Mills have passed 25% construction completion.  Applications become available on Monday, August 4th.  See details on applying at http://www.thbrightonmills.com/apply

101 and 107 Litchfield St are the two furthest along buildings.  Framing, taping, roofing, and window installation are complete. Remaining exterior work includes the installation of Hardie board siding and the construction of front porches. Inside, mechanical, electrical, and plumbing are well underway.

IMG_2785

IMG_2805

With progress on the other two Litchfield buildings moved inside, our contractors had space to complete excavation work for the final foundation at 103-105 Litchfield Street.

IMG_2819

Meanwhile on Holton Street.  Framing is proceeding quickly on the 121-123 Holton and 117-119 Holton buildings, with roofing nearing completion on 121-123 Holton.IMG_2811

Moving forward, framing will continue along Holton Street until the 113-115 Holton building is complete.  MEP work will shift from Litchfield to Holton Street.  Framing will move to the final building on Litchfield Street after the foundation is poured.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s