The Town Homes at Brighton Mills are nearing completion, with one month left to go before the first sales closings. It’s time for a photo walk-through of some of the features and finishes.
Siding, Priming, Pouring
With three months of construction remaining, the Town Homes at Brighton Mills are beginning to show their final shapes and shades both outside and inside.

Hardie board siding is being installed at 107 Litchfield Street town homes, while inside both 107 and 101 walls are being primed.
Over on Holton Street, concrete slabs for the outdoor front decks have been poured.
Peak Activity
There’s a little of everything on site this September from drywall, painting and priming inside the furthest along buildings to rough framing on the last building and significant site work with the construction of storm water retention systems.
Trim is being installed ahead of siding at 101 and 107 Litchfield St.
Meanwhile inside 101 and 107 Litchfield, walls are drywalled, taped and ready for priming to begin this week.
103-105 Litchfield is the last building to be framed up. Rough framing is passing the 2nd floor this week.
Also off Litchfield St, an extensive stormwater recharge system has been installed where the parking lot is to be built. This system will mitigate the potential environmental impact of heavy rains over impervious parking.
The Difference a Week Makes
At this stage of construction with many trades on site and activity going on at nearly every location simultaneously, there’s a lot of progress made in as short as one week.
On Litchfield Street, the front decks are being framed up at 101 and 107 Litchfield.
The slab foundation at 103-105 Litchfield is being finished.

And, the final digging to be done on Litchfield Street is well underway with excavation below what will be the parking lot for the construction of storm water retention systems.
A very important and exciting detail is being added inside the buildings after insulation and before drywall. The hat channels shown in the photos below create separation between the upper and lower units. Separation dampens vibrations – vibrations like kids running around, furniture moving, all the normal noise we would rather not hear from our neighbors.

The clip is connected to the truss with a mechanism that dampens vibration

The ceiling drywall will screw into these hat channels, which are connected to the clips in the previous photo, preventing transmission of noise and vibrations between floors.
That building at Holton and Antwerp that just began framing in last week’s entry? Here it is framed to the roof. The sheathing will finish installation by the end of this week.
August Update
Work has been progressing well across the Town Homes at Brighton Mills site this summer.
Framing is moving quickly on the Holton Street block. Holton Street framing will be complete by the end of August.
Back on Litchfield Street, the final foundation is being poured this week at 103-105 Litchfield. Framing and roofing were completed on the 101 and 107 Litchfield buildings. Mechanical, Electical, and Plumbing (MEP) work is complete at 101 and will finish this week inside 107. After MEP inspections, insulation work began at 101 and will begin at 107 next week.
Busy Summer
The Town Homes at Brighton Mills have passed 25% construction completion. Applications become available on Monday, August 4th. See details on applying at http://www.thbrightonmills.com/apply
101 and 107 Litchfield St are the two furthest along buildings. Framing, taping, roofing, and window installation are complete. Remaining exterior work includes the installation of Hardie board siding and the construction of front porches. Inside, mechanical, electrical, and plumbing are well underway.

With progress on the other two Litchfield buildings moved inside, our contractors had space to complete excavation work for the final foundation at 103-105 Litchfield Street.
Meanwhile on Holton Street. Framing is proceeding quickly on the 121-123 Holton and 117-119 Holton buildings, with roofing nearing completion on 121-123 Holton.
Moving forward, framing will continue along Holton Street until the 113-115 Holton building is complete. MEP work will shift from Litchfield to Holton Street. Framing will move to the final building on Litchfield Street after the foundation is poured.
Progress
The weather has been kind and construction has been moving at a steady pace on the Town Homes at Brighton Mills.
Rough framing is nearly complete at 101 Litchfield Street. Window installation and roofing will begin later this week.
107 Litchfield Street is just behing 101, with framing of the roof level to be completed by next week. When framing is complete on these two buildings on Litchfield Street, excavation will begin on the third and final foundation on this block.
Meanwhile on Holton Street, excavation is under way for the third and final foundation on this block. 
Framing has also begun on Holton Street at the corner of Telford. While framing and excavation are underway at the corners of this block, the completed concrete slab foundation for the middle building provides some staging room. Framing will proceed on that building after the foundation at the corner of Antwerp St is complete. 
Taking Shape
Framing is well underway on the 101 and 107 Litchfield Street buildings, both of which are framed up to the second floor now.
Inside the two bedroom first floor homes are taking shape. Below, you are looking from the living room into the kitchen and through walls into the laundry room, bedrooms, and rear exit.
Meanwhile on Holton Street, the 113-115 and 117-119 building foundations have been poured. In the photo below, the under-slab vapor barrier system is under construction. The final concrete pour for the foundation slab will go over the layers of underground plumbing, stone, insulation, and vapor barrier fabric and should happen this week. 
After the framing crews finish 101 and 107 Litchfield, they will move over to Holton St to frame these buildings and the crew working on Holton will move to Litchfield to build the foundation for the 103-105 Litchfield building and will finish the last foundation at 121-123 Holton when the framing is well underway on the other Holton buildings. This dance keeps everything progressing on these very tight sites without staging or storing off site.
Foundations Progress
Footing Pours
NEI has begun to pour concrete for the footings on which the slab on grade foundations will eventually sit. 101 and 107 Litchfield St are furthest along, with the other buildings following behind with framing for the footing pours or excavation. These footings shore up the structure and provide solidity below the frost line to ensure the buildings’ foundations remain solid and secure.





































